TEA Computers was selected by GCWC to design and construct GCWC Data Center and to leverage the existing Mission-Critical Billing System performance and transactions throughput to fulfill the business expanding requirements.
The solution Criteria has the following elements:
  1. Solution optimization.
  2. True Value-added functionalities.
  3. Choice of the best equipment to meet requirements.
  4. Considering the ongoing process of system operation to maximize simplicity & effectiveness.
A- Existing Billing System Leveraging
  • The Data Base IBM single core Xseries Servers are replaced by the State-of-the-art Fujitsu-Siemens Quad core Xeon based servers to afford the required throughput.
  • The new Fujitsu-Siemens clusters are connected to the IBM DS4000 Disk Storage system after upgrading it.
  • Oracle 10 DB and Billing applications are installed and run on the new platform.
B- New Data Center
  • TEA Computers Solution for GCWC data Center is based on Fujitsu-Siemens Blade Technology and FibreCat Disk Storage series.
  • The Server Blades are hosting the Data Center Microsoft Servers such as Exchange, ISA, Do main Controllers, DHCP and also Kaspersky security and antivirus system.
  • GCWC new WEB site is running also on Blade servers.
  • High availability and redundancy guided the Data center Design and implementation to meet the site operation requirements of 7x24 basis.